5月16日消息,液空福建工程项目部将低压塔送入冷箱内,空分装置大件吊装工作顺利结束,冷箱主体顺利完工。从春节后施工队正式入场至今不足两个月的时间,完成了空分主、氩冷箱主体结构安装、冷箱内塔的顺利吊装;比原计划提前一周时间,为400吨履带吊及时转场净化区域,配合750吨履带吊进行大件吊装工作提供了保障。为后续管道施工创造了条件。
May 16 message, the liquid air Fujian project will be sent to the low-pressure cold tower, air separation plant large hoisting work ended smoothly, the main body of the cold box was successfully completed. From the Spring Festival after the construction team formal admission so far less than two months time, completed the main air separation, argon cold box main structure installation, cold box tower hoisting smoothly than the original plan one week in advance for the 400-ton crawler crane timely Transfer purification area, with the 750-ton crawler crane lifting work provided a guarantee. Subsequent pipeline construction has created the conditions.