论文部分内容阅读
2010年3月,我区启动城乡风貌改造二期工程,并将其列入自治区政府为民办实事项目之一。截至2010年年底,二期工程共完成14个设区市、61个县(市、区)、168个乡镇、840个村屯、71631户的房屋外立面改造,占计划任务的103.2%,以及160个综合整治型村屯的29项综合整治项目;完成投资12.35亿元,占计划总投资8.53亿元的144.8%。如今,随着二期工程的圆满完成,三期工程也将启动。
In March 2010, the district started the second phase of urban-rural transformation and included it as one of the practical projects of the autonomous region. As of the end of 2010, Phase II completed a total of 1416 district-level cities, 61 counties (cities, districts), 168 towns and 840 village houses, and 71631 renovated facades, accounting for 103.2% of the planned tasks. As well as a total of 160 comprehensive treatment village of 29 comprehensive renovation project; completed an investment of 1.235 billion yuan, accounting for a total investment of 853 million yuan 144.8%. Now, with the successful completion of the second phase of the project, the third phase of the project will also start.