论文部分内容阅读
【摘 要】 为了使超灌桩头便于破除,将事先加工好的复合脱松套套入钢筋笼外露承台的主筋和声测管外端表面,使桩头混凝土和主筋及声测管不发生握裹;在桩头切除位置采用风镐垂直桩身方向钻孔,将分离楔子插入钻孔中,并采用外力进行敲击,直至桩头与桩身完全分离,然后利用起吊设备吊出上部桩头。可保证桩体的质量,加快施工进度,减少施工灰尘,确保操作工人的健康和环保施工,极具推广价值。
【关键词】 灌注桩;超灌桩头;整体破除
【Abstract】 In order to make the Higher pouring pile crown is easy to break, nested the processed in advance compound removal loose into the main reinforcement of reinforcing cage exposed cap and outer surfaces of harmonic measuring tube, pile crown concrete won’t be griped with main reinforcement and harmonic measuring tube; With air pick drill vertical direction the pile at the resection position of pile crown, insert the separation wedge into drill hole, with the external force to knock, until pile crown and pile body is separated completely, then hoist the upper pile crown with lifting appliance. It will ensure the quality of pile body, speed up the construction progress, reduce the construction dust, ensure the operating workers' health and environmental construction, with the great popularization value.
【Key Words】 Bored pile; Higher pouring pile crown; The whole break
在灌注桩的施工中,混凝土水下灌注施工方法运用比较普遍,为了保证桩顶混凝土强度达到设计等级,一般超灌高度控制在0.8~1.0m,因超灌高度比较大,而且桩径也大,超灌桩头的破除一直是一个难题。现在工程施工中,基本还一直采用传统的人工破除或人工辅助小型机械破除,耗费大量的人力物力,而且速度很慢,对桩体质量、桩体钢筋损伤大,和所要求的高效施工速度不相匹配。本文介绍了一种超灌桩头整体破除技术,可供借鉴。
1 工艺原理
在桩成孔后安装钢筋笼前,将事先加工好的复合脱松套直接套入钢筋笼外露承台的主筋和声测管外端表面,并将其位置固定保证不发生串动,并在桩桩顶标高环向设置截断箍;在基坑开挖完成后,拔除预埋的截断箍,采用风镐垂直桩身方向钻孔,钻孔深度只需要达到桩径的1/5即可,将分离楔子插入钻孔中,并采用外力进行敲击,直至桩头与桩身完全分离,然后利用起吊设备吊出超灌桩头。
2 施工工艺流程
3 施工要点
3.1施工准备:复合脱松套、截断箍等原材料准备齐全;钢筋笼按设计要求制作、绑扎,所有的竖向主筋,必须与桩轴平行,不可有折线。
3.2桩头钢筋安装复合脱松套:复合脱松套设置在桩头部分,下端进入桩体5~10cm,采用铅丝扎紧固定,保证其不发生串动,并采用塑料胶布将复合脱松套的上、下端均缠裹严密,防止水泥浆进入脱松套内,使超灌的桩头混凝土和主筋不发生握裹,如图1。复合脱松套选取硬质塑料管,直径宜比主筋直径大2~5mm,内灌粉煤灰或细砂,保证在灌注中不被混凝土挤扁失效。
3.3安装“截断箍”:在桩顶标高处绕桩周一圈,预埋截断箍(即钢丝绳外套外表光滑的软质塑料管,绕桩的主筋外侧一圈。钢丝绳端头余留长度10cm,以便日后拔出)。“截断箍”要沿主筋外侧绑在主筋的脱松套上并压住用扎丝扎紧,如图2,以免在浇捣混凝土或出现塌孔等意外状况时被挤到桩头混凝土内部,影响拔除。
3.4安放钢筋笼及砼浇筑:钢筋笼采用吊装安放,钢筋笼吊运及安放应确保不变形,吊送到孔内就位时对准桩孔,吊直扶稳,缓慢下沉,避免碰撞孔壁。要注意脱松套、截断箍等不被损坏。桩钢筋笼全部就位后,经隐蔽验收合格后进行砼浇筑。砼应连续浇筑,并控制导管埋入砼内的深度,采取预防钢筋笼上浮的措施。
3.5开挖承台基坑:等桩基强度达到70%后,开挖承台基坑,在承台基坑开挖过程中,露在桩头外的主筋和声测管必须保护好,不能损伤或弯曲,如有损伤或弯曲,应认直进行调直,否则对整体破除桩头不利。
3.6拔除“截断箍”:承台基坑开挖后,露出桩头。用铁锤敲击阴影部分砼,利用钢丝绳带动,拔出“截断箍”,可见水平一圈凹槽面(即截桩位置),如图3。
3.7钻楔子孔:采用小型钻孔设备(如风镐),在凹槽面处采用风镐垂直桩身方向钻孔,钻孔深度只需要达到桩径的1/5即可,在同一水平面、沿桩直径方向钻孔6~8个,即楔子孔,形成截桩薄弱面。
3.8采用楔子分离桩头:将分离楔子插入钻孔中,并采用外力进行敲击,直至钻孔处桩头与桩身完全分离,同时,采用液压设备水平方向顶凿一圈,将分离的桩头进行晃动(桩墩等短桩不适用本方法),确保桩头超灌混凝土与钢筋和桩身砼完全分离。
3.9钻孔、安装吊装用钢钎: 在桩头砼侧壁上的同一水平面、沿桩直径方向钻眼(纵、横向各打一对孔,共四个),打入钢钎,如图4。
3.10起吊桩头:往钢钎上挂好钢丝绳,用吊机或卷扬机垂直起吊,将桩头混凝土整体吊出基坑,放置在基坑周边设定好的桩头存放场地。
4 結语
对于直径1.5米左右的桩,传统的人工+风镐的方法破除桩头,两名工人一天只能破除5根,且在破除过程中对桩体钢筋损伤较大,产生的噪声或灰尘较多;采用超灌桩头整体破除施工技术,两名工人一天可破除10根以上,可减少人工50%,且对桩身和桩体钢筋无损伤,同时还可降低施工噪声,减少灰尘污染,有利于环境保护。
参考文献:
[1]中国建筑科学研究院.JGJ94-2008建筑桩基技术规范[S].北京:中国建筑工业出版社,2008.
[2]李小广.钻孔灌注桩桩头整体破除施工方法论述[J].科技传播,2012,07.
[3]王以盛,余波,高洋洋,王涛.灌注桩破除桩头的方法和质量控制[J].山西建筑,2013,13.
【关键词】 灌注桩;超灌桩头;整体破除
【Abstract】 In order to make the Higher pouring pile crown is easy to break, nested the processed in advance compound removal loose into the main reinforcement of reinforcing cage exposed cap and outer surfaces of harmonic measuring tube, pile crown concrete won’t be griped with main reinforcement and harmonic measuring tube; With air pick drill vertical direction the pile at the resection position of pile crown, insert the separation wedge into drill hole, with the external force to knock, until pile crown and pile body is separated completely, then hoist the upper pile crown with lifting appliance. It will ensure the quality of pile body, speed up the construction progress, reduce the construction dust, ensure the operating workers' health and environmental construction, with the great popularization value.
【Key Words】 Bored pile; Higher pouring pile crown; The whole break
在灌注桩的施工中,混凝土水下灌注施工方法运用比较普遍,为了保证桩顶混凝土强度达到设计等级,一般超灌高度控制在0.8~1.0m,因超灌高度比较大,而且桩径也大,超灌桩头的破除一直是一个难题。现在工程施工中,基本还一直采用传统的人工破除或人工辅助小型机械破除,耗费大量的人力物力,而且速度很慢,对桩体质量、桩体钢筋损伤大,和所要求的高效施工速度不相匹配。本文介绍了一种超灌桩头整体破除技术,可供借鉴。
1 工艺原理
在桩成孔后安装钢筋笼前,将事先加工好的复合脱松套直接套入钢筋笼外露承台的主筋和声测管外端表面,并将其位置固定保证不发生串动,并在桩桩顶标高环向设置截断箍;在基坑开挖完成后,拔除预埋的截断箍,采用风镐垂直桩身方向钻孔,钻孔深度只需要达到桩径的1/5即可,将分离楔子插入钻孔中,并采用外力进行敲击,直至桩头与桩身完全分离,然后利用起吊设备吊出超灌桩头。
2 施工工艺流程
3 施工要点
3.1施工准备:复合脱松套、截断箍等原材料准备齐全;钢筋笼按设计要求制作、绑扎,所有的竖向主筋,必须与桩轴平行,不可有折线。
3.2桩头钢筋安装复合脱松套:复合脱松套设置在桩头部分,下端进入桩体5~10cm,采用铅丝扎紧固定,保证其不发生串动,并采用塑料胶布将复合脱松套的上、下端均缠裹严密,防止水泥浆进入脱松套内,使超灌的桩头混凝土和主筋不发生握裹,如图1。复合脱松套选取硬质塑料管,直径宜比主筋直径大2~5mm,内灌粉煤灰或细砂,保证在灌注中不被混凝土挤扁失效。
3.3安装“截断箍”:在桩顶标高处绕桩周一圈,预埋截断箍(即钢丝绳外套外表光滑的软质塑料管,绕桩的主筋外侧一圈。钢丝绳端头余留长度10cm,以便日后拔出)。“截断箍”要沿主筋外侧绑在主筋的脱松套上并压住用扎丝扎紧,如图2,以免在浇捣混凝土或出现塌孔等意外状况时被挤到桩头混凝土内部,影响拔除。
3.4安放钢筋笼及砼浇筑:钢筋笼采用吊装安放,钢筋笼吊运及安放应确保不变形,吊送到孔内就位时对准桩孔,吊直扶稳,缓慢下沉,避免碰撞孔壁。要注意脱松套、截断箍等不被损坏。桩钢筋笼全部就位后,经隐蔽验收合格后进行砼浇筑。砼应连续浇筑,并控制导管埋入砼内的深度,采取预防钢筋笼上浮的措施。
3.5开挖承台基坑:等桩基强度达到70%后,开挖承台基坑,在承台基坑开挖过程中,露在桩头外的主筋和声测管必须保护好,不能损伤或弯曲,如有损伤或弯曲,应认直进行调直,否则对整体破除桩头不利。
3.6拔除“截断箍”:承台基坑开挖后,露出桩头。用铁锤敲击阴影部分砼,利用钢丝绳带动,拔出“截断箍”,可见水平一圈凹槽面(即截桩位置),如图3。
3.7钻楔子孔:采用小型钻孔设备(如风镐),在凹槽面处采用风镐垂直桩身方向钻孔,钻孔深度只需要达到桩径的1/5即可,在同一水平面、沿桩直径方向钻孔6~8个,即楔子孔,形成截桩薄弱面。
3.8采用楔子分离桩头:将分离楔子插入钻孔中,并采用外力进行敲击,直至钻孔处桩头与桩身完全分离,同时,采用液压设备水平方向顶凿一圈,将分离的桩头进行晃动(桩墩等短桩不适用本方法),确保桩头超灌混凝土与钢筋和桩身砼完全分离。
3.9钻孔、安装吊装用钢钎: 在桩头砼侧壁上的同一水平面、沿桩直径方向钻眼(纵、横向各打一对孔,共四个),打入钢钎,如图4。
3.10起吊桩头:往钢钎上挂好钢丝绳,用吊机或卷扬机垂直起吊,将桩头混凝土整体吊出基坑,放置在基坑周边设定好的桩头存放场地。
4 結语
对于直径1.5米左右的桩,传统的人工+风镐的方法破除桩头,两名工人一天只能破除5根,且在破除过程中对桩体钢筋损伤较大,产生的噪声或灰尘较多;采用超灌桩头整体破除施工技术,两名工人一天可破除10根以上,可减少人工50%,且对桩身和桩体钢筋无损伤,同时还可降低施工噪声,减少灰尘污染,有利于环境保护。
参考文献:
[1]中国建筑科学研究院.JGJ94-2008建筑桩基技术规范[S].北京:中国建筑工业出版社,2008.
[2]李小广.钻孔灌注桩桩头整体破除施工方法论述[J].科技传播,2012,07.
[3]王以盛,余波,高洋洋,王涛.灌注桩破除桩头的方法和质量控制[J].山西建筑,2013,13.