A Design of Prototype Planetary Rover

来源 :中国科技博览 | 被引量 : 0次 | 上传用户:pp6vip123
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
  中圖分类号:TP129 文献标识码:A 文章编号:1009-914X(2018)10-0368-02
  Introduction
  One of the questions which humanity has been discussing for millennia is whether there is life in the universe beyond our planet. Although this question may prove very difficult to answer, scientists have identified that Mars could potentially show evidence, through study of its geology, that it once contained water- a prerequisite for life. The SRC at the University of Leicester is currently running projects which are investigating this possibility, through analysing samples from comets and meteorites which come from Mars, and by developing equipment and instruments to perform relevant experiments. One such project is the SPLIT (Small Planetary Linear Impulse Tool), a tool which applies force to the outside of a rock in order to cleave it in two, thus exposing the inside surface without contaminating it by direct contact with scientific equipment.
  This device is designed for use on the surface of Mars, for which it would need to be mounted to a planetary rover. The idea of a remote-controlled, unmanned, planetary rover which could be sent into space to provide data about a planet or other body has been around for a long time, and the first successful rover mission was the Soviet Union’s Lunokhod 1, sent to the moon in 1970 [1]. Since then, rovers have been used to explore Mars, as its hostile conditions and distance make it impractical for manned mission currently. The Mars Exploration Rover (MER) mission, run by NASA, sent two rovers to Mars with the goals of exploring the planet’s surface and geology. Spirit, the first of the two, was in operation for about 6 years, while Opportunity, the second, is still in operation to this date. NASA has since sent another rover, called Curiosity, to Mars and it is also still functioning [2]. Curiosity had a more expanded set of goals, which were more focused on biological and geological investigations into the possibilities of life being possible on the planet. To accommodate this, it also featured a more comprehensive scientific test-bed and greater computing power. These designs have been used as inspiration for this project in many instances.
  Project Progression
  During the project defining and planning stage, an initial project plan was created to reflect the timeline throughout and to order tasks required to complete the project. The plan was both vague in some respects due to not knowing the full scope of tasks that would be needed but also contained very specific tasks in subsystems that team members had more experience in. The plan also contained initial estimates for resource distribution, with lead engineers designated for each sub-system and support engineers assigned so that members had someone to consult whilst overcoming design challenges and checking work.   Following conversations with the Space Research Centre, it was determined from an early stage that the workshop deadline was not applicable to the project due to an alternative manufacturing solution in the Physics workshop, where manufacturing could take place with much shorter notice. The deadline was still included as a target to aid with timeliness of the project as opposed to a requirement for project success in order to motivate the team to produce a suitably developed design in the early stages of the project.
  The initial plan was created using rough estimates from the team of what tasks would be required and how long they would take to complete. This also included initial resource allocation to foresee who would be loaded heavily at which points of the project. From this initial exercise of determining how much work each sub-system required, initial design restrictions were made to ensure project completion such as the simplification of steering design. Odometry was also planned but set to a low priority. This was due to time pressures being highlighted within the project where suitably qualified team members would not have enough availability to ensure the systems would be completed sufficiently, if at all.
  Throughout the early stages of the project, the team continued working with the initially proposed Gantt chart with little evolution of it until the management review with Martin Rhodes. At this point, it was suggested that an unmaintained project plan hampered project progression as opposed to keeping track of it. As a result of this, the team realised that the project plan must be a living document which is maintained and updated throughout the project to ensure it aids with project progression instead of impeding it. Therefore, the plan was reworked with greater task detail and more realistic timeline calculations to allow for easier management of the project.
  The initial plan contained tasks accounting for research within the individual sub-systems, however there was initially a small amount of disagreement between the Space Research Centre and the team as to the amount of time that should be spent on research. The team wanted to press ahead with design development stages of the project and had planned to do so, conscious of the time restrictions in place with pressures mounting in the manufacturing stages of the project; whereas the Space Research Centre wanted the team to spend a greater amount of time researching and preparing for designing.   For the first parts of the project, progression was mostly to schedule with only minor delays relating to the mechanical parts of the project. However, towards the end of semester 1, it became clear the initial plan was not an accurate representation of the requirements of the project and delays were arising particularly in the mechanical aspects of the project. Ample mechanical development had not been performed, highlighting the Space Research Centre’s previous concerns regarding initial research and requirements gathering. Therefore, development was extended, causing delays to the planned timeline. Although delays pushed the project off of the initial timeline, the developments allowed for a better and more suitable design, which also improved manufacturability and ease of assembly, which eased time pressures in the latter stages of the project. A factor which acted in favour of easing these time pressures was that as the workshop deadline target was not completely applicable to the project, this delay was not critical. Therefore, the deadline imposed by the team was not a critical milestone and could cope with a limited amount of delay.
  Further mechanical delays were encountered relating to design development and procurement when required parts became unavailable around the Chinese New Year period, making a prime source of components unavailable for a couple of weeks. This delay was negated during the manufacturing stage where mechanical assembly progress was limited, allowing the components to be delivered during the waiting period for manufacturing to be completed.
  The vision system was completed on schedule but only after resources were reallocated to provide additional support after decisions made over the Christmas break caused a major setback in its development. The original support engineers to fan, George and Qinyuan, could not spare the time required to fully provide support. Therefore, Ben was reallocated as support engineer for the vision system, resulting in its timely completion.
  The main control hub was completed in its most part on schedule, albeit additional hours were worked per week to ensure timely completion. This was due to an initial underestimation of the amount of work required to complete the system, with several additional aspects added later. As a result of this oversight, several aspects of the main control hub remain incomplete, however other factors have also hindered the system’s progress such as issues relating to the drive system. The drive system was completed to schedule throughout most of the project, however system assembly and testing proved extensive, causing delays and postponing whole system tests. Additional resources were allocated to this system in an attempt to mitigate this effect however the delays caused project completion to be delayed.
  Conclusion
  Overall, the project was completed largely to schedule within the early parts of the timeline, however inaccuracies in the early task duration estimates meant delays became inevitable within the middle parts of the project on some sub-systems. The management review highlighted errors in the initial plan and timeline recalculations were performed once it had been restructured. The delays present in the initial plan were later negated by recalculations in the second half of the project in the most part, whilst mechanical design developments initially causing delays were negated by improved ease of assembly. The combination of these factors ensured the majority of the project was completed on time.
  References
  [1]https://www.space.com/35090-lunokhod-1.html (last accessed 3/05/18)
  [2]https://www.space.com/37722-mars-rover-curiosity-five-years-anniversary.html (last accessed 3/05/18)
其他文献
[摘 要]新课改对于高中英语语法教学有了新的要求,使得教师对于合作学习更加关注。基于此,本文结合了笔者参与崇左市教育科学的规划课题“合作学习在高中英语语法教学中的应用”的实际教研经验,分析了合作学习对于高中英语语法教学的作用,阐述了合作学习在高中英语语法教学中的应用策略。  [关键词]合作学习;高中英语;语法教学  中图分类号:TP3 文献标识码:A 文章编号:1009-914X(2019)04-
期刊
[摘 要]在我国教育体制改革不断深入的背景下,我国中职教育水平得到了极大提升。然而,由于中职教育在我国起步较晚,教学中困难较大。中职英语口语教学中,由于学生英语基础差,加上教学不够规范,以至于英语口语教学中存在一定的问题,运用情境教学法,能够为学习者提供接近真实的口语环境,促进学生英语口语水平提升。  [关键词]情境教学法;中职英语;口语教学  中图分类号:TP3 文献标识码:A 文章编号:100
期刊
[摘 要]随着教育改革的逐步推进,在新课程理念指导下,高中英语课堂为了达到预期效果,开始采用小组合作学习的方式,提高学生的学习成绩。基于此,本文以新课程理念下高中英语课堂合作学习作为研究对象,通过对小组合作学习模式在高中英语课堂中的积极作用进行分析,探究高中英語课堂合作学习给学生带来的优势,分别从合理进行分组、课堂实施、掌握活动时机等方面详细阐述新课程理念下高中英语课堂合作学习的积极策略,从而提高
期刊
[摘 要]中职院校营销课程教学的目标是为了培养学生的市场营销职业能力,传统的课堂讲授方法是以老师为主体,并过于注重理论知识的传授,从而导致教学效果不理想,而乐学课堂是以学生为主体,注重教学模式的创新,从而提高教学质量。基于此,下文对营销教学中存在的问题进行了分析,并提出了构建乐学课堂的解决措施,希望对相关人员提供。  [关键词]市场营销教学;乐学课堂;问题  中图分类号:G712 文献标识码:A
期刊
[摘 要]近年来,随着经济和科技的快速发展,一些新的媒体逐渐诞生。这些新媒体的出现,加快了信息的传播速度,增强了媒体的互动性能,也改变了人们的生活方式。在这种背景下,广播电视台为了促进自身的发展,需要加强其维护工作的力度,保证其质量,提高广播电视技术维护工作的工作水平。本文就对广播电视技术维护管理工作的思考进行探讨,在介绍广播电视技术维护管理工作基本特点的基础上,提出了具体的维护管理措施,以供参考
期刊
[摘 要]设计了应用于塑料闪烁体探测器核脉冲信号处理的一种实用放大成形电路。该电路采用了高速运算放大器AD8045,利用巴特沃斯滤波电路实现了核脉冲信号的放大和改造,最后得到准高斯波形。阐述了电路的设计原理及作用并对实际电路进行了实验测试,给出了其技术性能指标及实验输出波形图。实验结果证明了该电路的可行性,也为其他探测器的核脉冲放大成形电路提供了一种简单实用的设计方法。  [关键词]核信号;放大;
期刊
[摘 要]在新旧媒体融合发展的背景下,新媒体由于具有灵活性、及时性、交互性等特点,迅速吸引了一大批受众,并对广播、电视等传统媒体产生了巨大的冲击影响。广播播音主持只有使自己的主持风格具有个性化,才能带给听众别样的收听感受,聚集一大批忠实的“粉丝”,实现收听率的稳步上升。因此,在融媒背景下探究广播播音主持风格个性化培养的可行性措施,也成为广播台提高自身竞争力的一种有效手段。  [关键词]媒体融合;播
期刊
[摘 要]航海的发展促进船舶更加先进,电气系统对保障整个船舶的安全运行起着重要作用,所以,必须高标准严要求地对船舶电气设备做定期检修及排查。基于此,本文以船舶电气设计中存在的主要问题为考察对象,就船舶的设计提出一些建议。  [关键词]船舶;电气设计;问题;措施  中图分类号:C912 文献标识码:A 文章编号:1009-914X(2019)04-0034-01  1船舶电气设计中的常见问题  1.
期刊
[摘 要]当今社会的进步促使人民生活水平的提高,人民的出行方式也发生了改变,随着车辆的增加人民对汽油的需求也不断提升。但是汽油是一种不可再生能源,大量的利用汽油将会导致汽油资源枯竭,因此相关管理人员就开始高度重视油气储运的问题。本文通过探讨输油管道控制阀门的设计与实现来保证油气在运输时更加合理,减少油气运输过多或者其他问题的发生。  [关键字]输油管道;控制阀门;设计与实现  中图分类号:C912
期刊
[摘 要]介绍了航空发动机外部管路的结构特点,简单讲解了外部管路感应钎焊的基本原理和对管路感应钎焊设备进行了介绍,就典型管路的感应钎焊工艺进行了详细讲述,重点就焊接变形控制技术讲解了密封接头感应钎焊的防变形技术。  [关键词]航空发动机;外部管路;感应钎焊;变形;接头;工艺  中图分类号:TG454 文献标识码:A 文章编号:1009-914X(2019)04-0043-01  1前言  管路是黎
期刊