摘要:随着我国人们日益所需的电力增长,从西部、北部地区向东部、南部地区输送电能也变得日益的重要。变电站在电力输送系统中有着重要的作用,所以变电站的工程设计施工在建筑业里属于特殊的工业建筑,不同于普通的民用建筑。由于变电站工程在设计施工中的特殊性和重要性,在施工的过程中难免会遇到各种较为复杂的问题。如何在施工中发现施工的重点,解决施工中的难点则关系着变电站的建设价值和意义。
关键词:变电站;施工重点;施工难点
Abstract: with China's increasing the power required for growth, from the west, north to south, East power transmission has become increasingly important. Substation plays an important role in the power transmission system, so the engineering design and construction of substation is a special industrial building in the construction industry, different from ordinary civil buildings. The substation project in the design and construction of special importance, in the construction process will inevitably encounter all kinds of complex problems. How to find the construction focus in construction, solve the difficulties in the construction of the value and significance of the construction of substation.
Keywords: substation; key construction; construction difficulties
中图分类号:TM63文献标识码:A文章编号:
随着我国经济的发展,人们生活水平的日益提高,人们对电力的需求也越来越多,而我国东部和南部地区的需电量要远远的高于西部和北部地区,所以因为环境、人口需求等因素影响,我国制定了“西电东送”的能源输送方针,可以更好的利用和平衡我国各地的能源,促进经济的发展,满足人们的生活、生产需要。在电力输送的过程中,变电站则发挥着至关重要的作用,因为变电站的特殊性和重要性使得变电站的设计施工工程也较为复杂化,不同于一般的施工工程,所以在设计和施工的过程中则会出现各种各样的难以解决的问题。本文以220KV的变电站施工为例,对在施工中所遇到的施工重点和难点进行分析探讨。
变电站的设计施工的特殊性
变电站的选址施工特点
变电站一般都要建设在人员稀少的地区,并且需要平坦开阔的场地,它的施工特点主要有:① 地面基础设备的需求量较大,土石方的工作量较大,砼工程量较大,砌石工程量相对较小;② 在设计和施工的工艺上要求有较高的质量,必须达到国家电网的达标投产要求;③ 施工中挖填量不平衡,平场的工作量较大,地面的设备和附属的建筑较多;④ 施工中防水系统较为复杂,专业性强,要有水喷雾系统,部分的施工中还需要考虑到防雷的措施;⑤ 由于施工的工期较长,需要生活用水和施工用水,所以需要就地打井,提供正常所需的用水。
变电站的总体施工特点
变电站应按照先地下、再地上,先土建、再电气、后进行调试,先主体、再装修,先高压、再低压、后其它(先220KV、再110KV),先综合(继电器室、通讯室、控制室等)、再附属,现构架、再支架的施工顺序进行施工建设。
变电站安装施工特点
3.1 所需的电缆量较大,型号较多,施工的工期较长。
3.2 主控室、继电器室和室外盘柜量较大,要求验收的规范和相关安装规范较为严格。
3.3 设备主要是有国产和合资厂生产,特殊性、专业性和技术水平要求较高,在安装和调试的工作中带来了较大的困难。
3.4 由于管母线种类较多,敷设的方式不同,所以在施工中要为以后的改造升级预留空间,导致施工的工程量较大。
变电站的施工重点
变电站在施工前的准备工作
1.1 材料的准备工作。为了完成施工的计划内容,建设方应按照施工方的要求及时的提供所需的设备和材料,如由施工方自行采买的材料和设备应有技术人员进行审核后提出合理的采购计划,对供货商进行筛选,签订采购合同。为了施工的工程进度和施工质量,所有的材料和设备必须要符合要求,并且资料齐全,有产品的合格证,当场进行清点验收。
1.2 技术资料的准备工作。施工的技术资料主要有施工规范、各类质量验收表格、施工资料的编制、验收标准等,该项工作应由工程的总工进行组织,由技术人员负责施工规范、验收标准、质量验收表格、技术资料编制等工作。
变电站的施工顺序要点
2.1 220KV、110KV构支架的要点。构支架应使用铁件、水泥杆加工,构支架的质量对组装的质量有十分重要的影响。
2.2 一次性设备的基础要点。对预留设备的基础大小、水平和垂直度、形状应严格的进行查看,达到电气设备安装的要求。
2.3 二次設备的安装要点。在安装前应对设备的内部配置进行检查,标明安装的地点和用途,在设备就位的过程中要有防震措施,保证达到安装的要求。二次接线应按照安装图纸进行,确保接线的准确性。
2.4 明沟和电缆沟的施工要点。沟底应有排水的坡度,防止沟内积水,墙体砌筑和沟底标高要按照设计的要求进行,沟内的预理件要现进行焊接再进行掩埋,要保证位置的准确性,沟盖板的表面要保证光洁,死角四棱的厚度要均匀。
变电站施工的难点
电气工程施工的难点
电气施工应按照先设备、再电缆,先安装、再调试的程序进行,为了减少设备的二次装运和保管的工作量,应及时的和供货商进行沟通,所需设备应按照要求到货,并按照设备的安装场地就近堆放。
带电施工
2.1 施工时要对站内地线进行检查,保证已全部拆除,全部的开关和信号位置都处于断开的状态。
2.2 保证电气设备安装调试都已经完成并且达到合格的标准,记录完整,所有的带电部位都全部拆除完毕,在检查中发现的缺陷都得到了合理的处理,达到带电运行的标准。
2.3 按照设计的要求确保变电站的一、二次和辅助设备及所有的电气设备试验均已合格,可以投入使用。
参考文献:
[1] 高建文,王晓克.浅谈变电站的设备安装施工[J].中国科技博览,2011,(6):61-61.
[2]Tohid Akbari,Mohammad Heidarizadeh,Majid Abdi Siab,et al.Towards integrated planning: Simultaneous transmission and substation expansion planning[J].Electric Power Systems Research,2012,86:131-139.
[3] 冯健广.浅谈变压器铁芯故障的诊断与排除[J].中国高新技术企业,2009,(20):26-28.
关键词:变电站;施工重点;施工难点
Abstract: with China's increasing the power required for growth, from the west, north to south, East power transmission has become increasingly important. Substation plays an important role in the power transmission system, so the engineering design and construction of substation is a special industrial building in the construction industry, different from ordinary civil buildings. The substation project in the design and construction of special importance, in the construction process will inevitably encounter all kinds of complex problems. How to find the construction focus in construction, solve the difficulties in the construction of the value and significance of the construction of substation.
Keywords: substation; key construction; construction difficulties
中图分类号:TM63文献标识码:A文章编号:
随着我国经济的发展,人们生活水平的日益提高,人们对电力的需求也越来越多,而我国东部和南部地区的需电量要远远的高于西部和北部地区,所以因为环境、人口需求等因素影响,我国制定了“西电东送”的能源输送方针,可以更好的利用和平衡我国各地的能源,促进经济的发展,满足人们的生活、生产需要。在电力输送的过程中,变电站则发挥着至关重要的作用,因为变电站的特殊性和重要性使得变电站的设计施工工程也较为复杂化,不同于一般的施工工程,所以在设计和施工的过程中则会出现各种各样的难以解决的问题。本文以220KV的变电站施工为例,对在施工中所遇到的施工重点和难点进行分析探讨。
变电站的设计施工的特殊性
变电站的选址施工特点
变电站一般都要建设在人员稀少的地区,并且需要平坦开阔的场地,它的施工特点主要有:① 地面基础设备的需求量较大,土石方的工作量较大,砼工程量较大,砌石工程量相对较小;② 在设计和施工的工艺上要求有较高的质量,必须达到国家电网的达标投产要求;③ 施工中挖填量不平衡,平场的工作量较大,地面的设备和附属的建筑较多;④ 施工中防水系统较为复杂,专业性强,要有水喷雾系统,部分的施工中还需要考虑到防雷的措施;⑤ 由于施工的工期较长,需要生活用水和施工用水,所以需要就地打井,提供正常所需的用水。
变电站的总体施工特点
变电站应按照先地下、再地上,先土建、再电气、后进行调试,先主体、再装修,先高压、再低压、后其它(先220KV、再110KV),先综合(继电器室、通讯室、控制室等)、再附属,现构架、再支架的施工顺序进行施工建设。
变电站安装施工特点
3.1 所需的电缆量较大,型号较多,施工的工期较长。
3.2 主控室、继电器室和室外盘柜量较大,要求验收的规范和相关安装规范较为严格。
3.3 设备主要是有国产和合资厂生产,特殊性、专业性和技术水平要求较高,在安装和调试的工作中带来了较大的困难。
3.4 由于管母线种类较多,敷设的方式不同,所以在施工中要为以后的改造升级预留空间,导致施工的工程量较大。
变电站的施工重点
变电站在施工前的准备工作
1.1 材料的准备工作。为了完成施工的计划内容,建设方应按照施工方的要求及时的提供所需的设备和材料,如由施工方自行采买的材料和设备应有技术人员进行审核后提出合理的采购计划,对供货商进行筛选,签订采购合同。为了施工的工程进度和施工质量,所有的材料和设备必须要符合要求,并且资料齐全,有产品的合格证,当场进行清点验收。
1.2 技术资料的准备工作。施工的技术资料主要有施工规范、各类质量验收表格、施工资料的编制、验收标准等,该项工作应由工程的总工进行组织,由技术人员负责施工规范、验收标准、质量验收表格、技术资料编制等工作。
变电站的施工顺序要点
2.1 220KV、110KV构支架的要点。构支架应使用铁件、水泥杆加工,构支架的质量对组装的质量有十分重要的影响。
2.2 一次性设备的基础要点。对预留设备的基础大小、水平和垂直度、形状应严格的进行查看,达到电气设备安装的要求。
2.3 二次設备的安装要点。在安装前应对设备的内部配置进行检查,标明安装的地点和用途,在设备就位的过程中要有防震措施,保证达到安装的要求。二次接线应按照安装图纸进行,确保接线的准确性。
2.4 明沟和电缆沟的施工要点。沟底应有排水的坡度,防止沟内积水,墙体砌筑和沟底标高要按照设计的要求进行,沟内的预理件要现进行焊接再进行掩埋,要保证位置的准确性,沟盖板的表面要保证光洁,死角四棱的厚度要均匀。
变电站施工的难点
电气工程施工的难点
电气施工应按照先设备、再电缆,先安装、再调试的程序进行,为了减少设备的二次装运和保管的工作量,应及时的和供货商进行沟通,所需设备应按照要求到货,并按照设备的安装场地就近堆放。
带电施工
2.1 施工时要对站内地线进行检查,保证已全部拆除,全部的开关和信号位置都处于断开的状态。
2.2 保证电气设备安装调试都已经完成并且达到合格的标准,记录完整,所有的带电部位都全部拆除完毕,在检查中发现的缺陷都得到了合理的处理,达到带电运行的标准。
2.3 按照设计的要求确保变电站的一、二次和辅助设备及所有的电气设备试验均已合格,可以投入使用。