武钢一米七冷轧工程大件数量较多,计5829件,共重39000余吨。体积颇大,多数是长方形,少数是圆筒形,个别为球形。由于装卸机具和运输车辆不足,所以大件运输矛盾比较突出。从西德资料中了解,他们国家的公路大都是一、二、三级路面,而武钢厂区及厂区附近的道路坑洼不平,施工现场排水不好,运输条件差。为使大件安全,及时地运到冷轧工地,我们在总结武钢和外包
The number of large-scale projects of the 1.7-meter cold-rolled steel rolling mill at Wuhan Iron and Steel Company is relatively large, accounting for 5,829 pieces and weighing over 39,000 tons. The volume is quite large, most of which are rectangular, a few are cylindrical, and individual are spherical. Due to the shortage of loading and unloading equipment and transport vehicles, the contradiction between large-scale transportation is more prominent. According to the information from West Germany, the roads in their country are mostly grades I, II, and III, and the roads near the plant area and the plant area of Wuhan Iron and Steel Company are uneven. Drainage on the construction site is not good and transportation conditions are poor. In order to make large parts safe and timely transported to the cold-rolled construction site, we are summarizing WISCO and outsourcing