现浇柱预制梁框架结构的梁柱节点构造为浇注整体型。这类框架结构具有整体性好,节约模板、支撑,不需钢筋剖口接头焊接,工期较短等优点。现浇柱预制梁框架中,柱的施工方法与一般现浇框架柱相同。现根据我部的施工实践介绍以下三种安装预制梁的方法: 一、临时支柱法本方法是在横梁设计位置的两端各支撑一根临时钢管或木支柱,以承受横梁、楼板和施工荷载。钢管支柱作为工具式支撑,可在类似工程中重复使用。某五层现浇柱预制梁框架结构的电化教
The beam-column node structure of the cast-in-place prefabricated beam frame structure is a cast integral type. This type of frame structure has good integrity, saves formwork and supports, does not require rebar joint welding, and has a shorter construction period. In cast-in-place prefabricated beam frames, the construction method of columns is the same as that of cast-in-situ frame columns. According to our department’s construction practice, we will introduce the following three ways to install prefabricated beams: 1. Temporary pillar method This method is to support one temporary steel pipe or wooden pillar at both ends of the beam design position to bear the beam, floor and construction load. . Steel pipe pillars are used as tool supports and can be reused in similar projects. Electrochemical teaching of a five-storey cast-in-place prefabricated beam frame structure