【摘 要】 BDF薄板箱体是近年新开发的现浇混凝土空心楼板内模形式。采用此种方式的空心楼板设计计算方法简便,施工操作方便,可实现较大的空心率。现浇混凝土空心楼板由于置入了内模,减少混凝土用量从而减轻自重,降低工程造价,减少地震作用,同时增大建筑净高和跨度,提高了有效空间。该技术提高了大楼隔音隔熱效果,保证了楼板面整齐平整,也保证了建筑风格及实用功能。
【关键词】 混凝土工程;BDF薄壁空心楼板;施工技术
BDF thin-walled hollow floor construction technology
Lianyun Wan
China State Construction Civil Construction Co., Ltd. 10000
【Abstract】 in recent years the BDF sheet is a new development of cast-in-situ concrete hollow floor internal model form. Hollow floor design calculation methods in this way is simple, easy to operate construction and can achieve a larger hollowness. Due to the placement of the inner die, cast-in-situ concrete hollow floor reduce the amount of concrete so as to reduce weight,the construction cost and the earthquake action, at the same time increase the building clear height and span, then improve the effective space. The technology not only improve the building sound insulation effect, but also ensure the floor surface tidy flat, the building style and practical function.
【Key Words】 Concrete Engineering;BDF Thin-walled hollow floor;Construction Technology
1 工程概况
本工程为武警总部司令部直属工作部筹建的556工程办公大楼,位于北京市海淀区西三环北路1号,建筑面积36947m2,共16层,柱网尺寸:15×24m,标准层高4.2m,总建筑高度74.7m。框架抗震等级一、三级,基本风压:0.5KN/m2,基本雪压0.45KN/m2,活载为1.0-4.0KN/m2。楼面二层~十二层4-7/C-E处采用BDF空心薄壁箱体为内模的现浇混凝土空心楼板。该工程2007年6月15日开工,2008年1月20日主体结构封顶。
2 新技术简介
现浇混凝土空心楼板就是按一定规则放置埋入式内模后,经现场浇筑混凝土而在楼板中形成空腔的楼板。“内模”即为埋置在现浇混凝土空心楼板中用以形成空腔且不取出的物体。本工程采用的“内模”为BDF空心薄壁箱体,主要起到规范成孔形状的作用,不参与结构受力。当混凝土成型,达到设计强度后,内模也就完成了“工作使命”。
BDF薄壁箱体(空心箱模)是近年来新开发的现浇混凝土空心楼板内模形式。采用此种方式的空心楼板设计计算方法简便,施工操作方便,可实现较大的空心率。现浇混凝土空心楼板由于置入了内模,从而减轻自重,减少混凝土用量,增大了跨度,提高了有效空间,且隔音隔热效果也很好。该项成果可广泛适用于大跨度、大空间、大荷载的建筑中。与传统技术相比较,可节省混凝土量,降低综合造价。该成果主要适用于学校、桥梁、阅览室、办公写字楼、商场、厂房、地下停车场、大开间住宅等项目。目前发展趋势看好,前景无限,与人民生活紧密相关,符合国家产业政策。该项成果的普及推广将可产生很好的综合效益。
现浇空心楼板结构(空心箱模)将空心箱模按照设计埋置于现浇混凝土楼板中,是近年发展起来的一项较新的技术,它根据钢筋混凝土结构受力原理,力求节约楼板截面中间受力较小区域内的混凝土,把现浇实心楼板整体性好和预制空心楼板自重轻、跨度大等优点巧妙地结合到一起。
3 施工工艺
3.1工艺流程
弹钢筋和箱模安放位置线——绑扎楼板底铁和肋梁——铺设预埋管线——设置抗浮固定点——检查验收抗浮点设置——安装空心箱模下部垫块——安装空心箱模——绑扎楼板上铁——搭设施工便道、架设砼输送管——隐蔽验收——砼浇筑
3.2施工要点
(1)施工准备
楼板模板支完并通过预检验收,框架结构的框架梁钢筋等已绑扎完成。
(2)弹钢筋和箱模安放位置线
按照设计排箱图要求,在楼板模板上放线,保证后续肋梁钢筋绑扎和箱模安装的位置准确。依据轴线,放出纵横向肋梁控制线,肋梁间即是安放箱模位置。在模板上放线可采用红白油漆等代替墨汁,以保证所放线的清晰牢固。
(3)绑扎楼板底铁和肋梁
按照模板上弹线的位置,依次绑扎楼板中的框架梁及暗梁。再按照绑梁的方法绑扎楼板肋梁;然后,铺设楼板下铁钢筋;肋梁钢筋和楼板下铁钢筋绑扎牢固。绑扎完毕后,拉线检查并调整好肋梁的位置、顺直。注意保证区格板周边和柱周围楼板设计实心部分的尺寸。预应力筋一般设置在肋梁内,在绑扎肋梁时,应进行预应力筋的铺设和绑扎。预应力筋张拉端和锚固端布置在板周边的框架梁等实心构件内。 (4)铺设预埋管线
楼板内的强弱电预埋管线等,应尽量沿着肋梁并布置在肋梁截面内,避开箱模位置;外径15mm以下的小直径管线也可铺设在箱模下部,但不超过一层,不得在箱模下交叉,以免垫高箱模。
对局部管线密集、管径大的部位,应尽可能集中布置在同一箱模跨内,在此部分换用小型薄壁空心楼板或换用聚苯板代替(聚苯板要外缠塑料胶带等保护)。
(5)设置抗浮固定点
楼板下铁和肋梁钢筋绑扎完毕后,即可开始设置抗浮点。抗浮点设置的抗浮传力途径如下:箱模上浮力——楼板上铁——肋梁箍筋或铁丝连接——楼板底铁——抗浮点铁丝——模板体系。抗浮点采用12号铁丝,用手电钻(采用Φ4钻头)在楼板下铁筋及肋梁下铁交叉处的两侧模板打孔,铁丝穿过模板在模板龙骨一侧拧紧,将楼板下铁及肋梁下铁与模板固定牢固。抗浮点沿箱体四角设置。应再用12号铁丝将楼板上铁筋与肋梁上铁绑扎拧紧,与下铁抗浮点对应设置,保证抗浮效果。(见图3、图4)
(6)检查验收抗浮点设置
抗浮点设置是现浇空心楼盖施工的关键。抗浮点设完成后,应进行抗浮点专项中间检查验收,以保证抗浮点设置均匀,位置准确,固定牢固可靠,满足抗浮要求。
(7)安装空心箱模下部垫块
在空心箱模下设置垫块,保证箱模下部的混凝土厚度。垫块厚度要符合箱模下部混凝土的设计厚度要求。设置数量,对于500*500的箱模,可只在箱模中间设置一块,对于尺寸较大的箱模,应根据需要设置,能保证箱模下部混凝土厚度为准。
(8)安装空心箱模
空心箱模的吊运可采用焊接好的敞口钢筋笼或其他箱式工具,钢筋笼内侧四边和底面用多层板封闭。按照排箱图,在每个肋梁空格内依次摆放,放置平整,前后左右对齐、对正。在箱体四周小密肋梁钢筋应保持钢筋保护层距离;或在箱体四个侧面箍筋上各放置1~2个10mm厚的小垫块,以保证箱体与小密肋梁之间的保护层厚度。对局部管线密集、管径大的部位,不能放置厚的箱模时,可換用小型薄壁空心楼板或换用聚苯板代替(聚苯板要外缠塑料胶带等保护);管线集中部位也可换小尺寸箱模避让;当预留预埋设施无法避开箱模时,可对箱模采取小型薄壁板或断开等措施,但事后应胶带和聚苯板等封堵严密。对于有些肋梁空格不满足箱模尺寸的,可将箱模锯开,空腔内填塞聚苯板等轻质材料,并用胶带封堵严密后使用。箱模安放后,应注意成品保护,避免人员频繁踩踏、破坏。破损的箱模,应在绑扎上铁前及时更换。
(9)绑扎楼板上铁
空心箱模安放完成后,即可开始绑扎楼板上铁。并与肋梁钢筋绑扎牢固。为保证抗浮点的有效,楼板上铁要压在肋梁上铁下,否则应单独设置上铁抗浮点与下铁抗浮点对应连接。
楼板上铁绑扎完毕后,在每个空心箱模顶和楼板上铁之间加设垫块,压住箱模,并保证箱模上部混凝土厚度。如下图:绑扎上铁钢筋加上铁垫块
(10)搭设施工便道、架设砼输送管
箱模本身有一定的强度,但频繁踩踏也容易造成损坏,尤其加完顶部垫块后,受力集中,易损坏。应用脚手板搭设架空施工便道,方便施工操作人员操作、通行,并保护箱模和楼板钢筋成品。
混凝土输送泵管不应直接架在楼板钢筋上,可搭设短管架子或垫木方等将泵管架高,布料杆等安放位置应提前安排好,布料杆应用脚手板和架子架高,不得直接压在箱模上。
施工机具等不得放置在空心箱模上,施工操作人员不得踩踏空心箱模。
(12)砼浇筑
现浇混凝土空心楼盖结构浇筑用混凝土,其塌落度应比普通实心楼盖稍大,可取18~20cm,不宜小于16cm;粗骨料粒径宜选择不超过5~25mm,且不大于箱模与模板间距的1/2,也不应大于肋梁宽的1/2。
箱模本身属水泥制品,在混凝土浇筑前应先洒水润湿(冬季不应洒水)。
混凝土浇筑宜采用泵送。浇筑沿楼板跨度方向从一侧开始,顺序依次进行,布料尽量均匀,避免砼在同一位置堆积过高损坏箱模。
振捣棒沿肋梁位置顺浇筑方向依次振捣,比实心楼板应适当加大振捣时间和振捣点数量,振捣同时观察空心箱模四周,直至不再有气泡冒出,表示箱模底部混凝土已密实;振捣棒应避免直接触碰空心箱模。
浇筑过程中如遇空心箱模损坏,必须及时处理。可用聚苯板、尼龙编织袋等轻质物品塞入损坏处封堵严密,注意不要使后塞物品露出箱模表面,造成混凝土夹渣。
4 施工中应注意的几个问题
1、施工中起拱方式:模板是双向板应双向起拱,单向板应单向起拱,应根据设计提供的起拱高度施工,有预应力的模板中心起拱高度在2‰。
2、空心箱体运达到施工现场后卸车时不得直接往地面上抛,堆放要整齐,不得用较重物件对空心箱体进行砸和压,放在地面和钢筋作业面上要稳定。安装空心箱体时必须轻拿轻放,在空心箱体安装过程中施工人员不得直接在空心箱体上面行走,在空心箱体上面行走之前应当铺设木板,不得直接在空心箱体上面堆放重物和其它作业。吊运安装时必须使用专用吊蓝吊运,严禁用缆绳直接绑扎空心管进行吊运,空心箱体被吊到安装楼层后应及时排放,不宜再叠层堆放。
3、振捣方法:在浇灌混凝土不宜直接在空心箱体上面堆积混凝土,放完的混凝土应立即摊开振捣、必须坚持少浇勤振,防止楼板下面出现露钢筋现象。振捣沿箱体四周的肋梁进行振捣,看见箱体中间的排气空洞中有混凝土反出,则代表下部混凝土已浇筑密实。振捣混凝土时易选用d=30的震捣棒,不得使用平板振捣器。
4、混凝土的浇筑方法:在浇筑混凝土时,应从一个角开始浇筑,依次逐步后退进行浇筑。下料时不应直接浇在空心箱体上或箱体中间的排气孔中,而是浇筑在框架梁或肋梁上。
5 结语
在几年的工程施工过程中,一直接触的都是混凝土楼板的施工,跨度都在6m~8m左右,跨距较小。在施工楼板过程中,存在十字交叉次梁或平行的次梁,给工人支设模板施工带来很多不便。与传统楼板施工技术相比,空心楼盖施工技术的最大区别与优势是: 1、施工中楼板的支模速度明显加快,整体铺放整块的模板,不用像传统楼板施工还要支设次梁的模板;
2、楼板中没有下反次梁,模板基本上不用破坏,整块拼装,使模板的周转次数明显增加,大大降低了施工成本;
3、在钢筋绑扎过程中省去了次梁,比传统提高了绑扎钢筋的成型速度,加快了施工进度。
4、在拆模过程中,比传统拆模快速方便,拆模过程不用再像以前有梁楼板不容易拆卸,拆卸后模板有碎块,模板的破损率高。采用空心箱体模板只要按顺序依次拆下,不费力气,模板完整,可以整体用到下一层去,增加了模板的周转次数、减少损耗、降低模板成本。
现浇混凝土空心楼板技术克服了传统预制混凝土空心楼板整体性差、跨度小、楼板出现裂缝、漏水,隔音不好等诸多不利因素。新技术的核浇心工艺是在现浇的楼板内放置永久的内模,节省楼板内不参与抗压抗拉等受力的混凝土,节省资源。由于整体筑,无缝隙,整体性受力非常好。另外,现浇整体空心板,比原来传统的预制空心板,在跨度方面有重大突破。在8m~15m跨度内完全不用预应力技术,降低工程成本,加快施工进度。目前该项目在新技术提供方鼎基建材(广西)科技开发有限公司的密切配合下,实施非常顺利,效果良好。同时,经常有设计单位、开发单位及施工单位前来现场观摩指导,在施工的规范程度、施工拆模后的质量、以及大空间效果等方面,得到了各界朋友的高度评价。笔者谨希望在今后的实践中,就现浇混凝土空心楼板新技术工艺的经验,与同行一起深入探讨。
参考文献:
[1]《现浇混凝土空心楼盖技术规程》,中国建筑科学研究院,中国计划出版社,2005年4月, 2.29.32.33.
[2] 建筑施工手册(第四版).[M]北京:中国建筑工业出版社,2003.
Building Construction Handbook (The fourth edition).[M]Beijing:China Architecture & Building Press, 2003.
[3] 建筑变形测量规范,JGJ8-2007,北京:中国建筑工业出版社,2007.
Code for deformation measurement of building and structure JGJ8-2007, Beijing:China Architecture & Building Press, 2007.
[4] 建筑工程冬期施工规程,JBJ/T104-2011, 北京:中国建筑工业出版社,2011.
Specification for winter construction of building engineering, JBJ/T104-2011, Beijing:China Architecture & Building Press, 2011.
[5] 混凝土结构工程施工质量验收规程,DBJ01-82-2005,北京:中國市场出版社,2005.
Specification for Acceptance of Constructional Quality of Concrete Structures, DBJ01-82-2005, Beijing:China Market Press, 2005.
[6] 建筑机械使用安全技术规程,JGJ33-2012,北京:中国建筑工业出版社,2012.
Technical specification for safety operation of constructional machinery, JGJ33-2012, Beijing:China Architecture & Building Press, 2012.
[7] 建筑节能工程施工质量验收规范,GB50411-2007,北京:中国建筑工业出版社,2007.
Code for acceptance of energy efficient building construction,GB50411-2007, Beijing:China Architecture & Building Press, 2007.
【关键词】 混凝土工程;BDF薄壁空心楼板;施工技术
BDF thin-walled hollow floor construction technology
Lianyun Wan
China State Construction Civil Construction Co., Ltd. 10000
【Abstract】 in recent years the BDF sheet is a new development of cast-in-situ concrete hollow floor internal model form. Hollow floor design calculation methods in this way is simple, easy to operate construction and can achieve a larger hollowness. Due to the placement of the inner die, cast-in-situ concrete hollow floor reduce the amount of concrete so as to reduce weight,the construction cost and the earthquake action, at the same time increase the building clear height and span, then improve the effective space. The technology not only improve the building sound insulation effect, but also ensure the floor surface tidy flat, the building style and practical function.
【Key Words】 Concrete Engineering;BDF Thin-walled hollow floor;Construction Technology
1 工程概况
本工程为武警总部司令部直属工作部筹建的556工程办公大楼,位于北京市海淀区西三环北路1号,建筑面积36947m2,共16层,柱网尺寸:15×24m,标准层高4.2m,总建筑高度74.7m。框架抗震等级一、三级,基本风压:0.5KN/m2,基本雪压0.45KN/m2,活载为1.0-4.0KN/m2。楼面二层~十二层4-7/C-E处采用BDF空心薄壁箱体为内模的现浇混凝土空心楼板。该工程2007年6月15日开工,2008年1月20日主体结构封顶。
2 新技术简介
现浇混凝土空心楼板就是按一定规则放置埋入式内模后,经现场浇筑混凝土而在楼板中形成空腔的楼板。“内模”即为埋置在现浇混凝土空心楼板中用以形成空腔且不取出的物体。本工程采用的“内模”为BDF空心薄壁箱体,主要起到规范成孔形状的作用,不参与结构受力。当混凝土成型,达到设计强度后,内模也就完成了“工作使命”。
BDF薄壁箱体(空心箱模)是近年来新开发的现浇混凝土空心楼板内模形式。采用此种方式的空心楼板设计计算方法简便,施工操作方便,可实现较大的空心率。现浇混凝土空心楼板由于置入了内模,从而减轻自重,减少混凝土用量,增大了跨度,提高了有效空间,且隔音隔热效果也很好。该项成果可广泛适用于大跨度、大空间、大荷载的建筑中。与传统技术相比较,可节省混凝土量,降低综合造价。该成果主要适用于学校、桥梁、阅览室、办公写字楼、商场、厂房、地下停车场、大开间住宅等项目。目前发展趋势看好,前景无限,与人民生活紧密相关,符合国家产业政策。该项成果的普及推广将可产生很好的综合效益。
现浇空心楼板结构(空心箱模)将空心箱模按照设计埋置于现浇混凝土楼板中,是近年发展起来的一项较新的技术,它根据钢筋混凝土结构受力原理,力求节约楼板截面中间受力较小区域内的混凝土,把现浇实心楼板整体性好和预制空心楼板自重轻、跨度大等优点巧妙地结合到一起。
3 施工工艺
3.1工艺流程
弹钢筋和箱模安放位置线——绑扎楼板底铁和肋梁——铺设预埋管线——设置抗浮固定点——检查验收抗浮点设置——安装空心箱模下部垫块——安装空心箱模——绑扎楼板上铁——搭设施工便道、架设砼输送管——隐蔽验收——砼浇筑
3.2施工要点
(1)施工准备
楼板模板支完并通过预检验收,框架结构的框架梁钢筋等已绑扎完成。
(2)弹钢筋和箱模安放位置线
按照设计排箱图要求,在楼板模板上放线,保证后续肋梁钢筋绑扎和箱模安装的位置准确。依据轴线,放出纵横向肋梁控制线,肋梁间即是安放箱模位置。在模板上放线可采用红白油漆等代替墨汁,以保证所放线的清晰牢固。
(3)绑扎楼板底铁和肋梁
按照模板上弹线的位置,依次绑扎楼板中的框架梁及暗梁。再按照绑梁的方法绑扎楼板肋梁;然后,铺设楼板下铁钢筋;肋梁钢筋和楼板下铁钢筋绑扎牢固。绑扎完毕后,拉线检查并调整好肋梁的位置、顺直。注意保证区格板周边和柱周围楼板设计实心部分的尺寸。预应力筋一般设置在肋梁内,在绑扎肋梁时,应进行预应力筋的铺设和绑扎。预应力筋张拉端和锚固端布置在板周边的框架梁等实心构件内。 (4)铺设预埋管线
楼板内的强弱电预埋管线等,应尽量沿着肋梁并布置在肋梁截面内,避开箱模位置;外径15mm以下的小直径管线也可铺设在箱模下部,但不超过一层,不得在箱模下交叉,以免垫高箱模。
对局部管线密集、管径大的部位,应尽可能集中布置在同一箱模跨内,在此部分换用小型薄壁空心楼板或换用聚苯板代替(聚苯板要外缠塑料胶带等保护)。
(5)设置抗浮固定点
楼板下铁和肋梁钢筋绑扎完毕后,即可开始设置抗浮点。抗浮点设置的抗浮传力途径如下:箱模上浮力——楼板上铁——肋梁箍筋或铁丝连接——楼板底铁——抗浮点铁丝——模板体系。抗浮点采用12号铁丝,用手电钻(采用Φ4钻头)在楼板下铁筋及肋梁下铁交叉处的两侧模板打孔,铁丝穿过模板在模板龙骨一侧拧紧,将楼板下铁及肋梁下铁与模板固定牢固。抗浮点沿箱体四角设置。应再用12号铁丝将楼板上铁筋与肋梁上铁绑扎拧紧,与下铁抗浮点对应设置,保证抗浮效果。(见图3、图4)
(6)检查验收抗浮点设置
抗浮点设置是现浇空心楼盖施工的关键。抗浮点设完成后,应进行抗浮点专项中间检查验收,以保证抗浮点设置均匀,位置准确,固定牢固可靠,满足抗浮要求。
(7)安装空心箱模下部垫块
在空心箱模下设置垫块,保证箱模下部的混凝土厚度。垫块厚度要符合箱模下部混凝土的设计厚度要求。设置数量,对于500*500的箱模,可只在箱模中间设置一块,对于尺寸较大的箱模,应根据需要设置,能保证箱模下部混凝土厚度为准。
(8)安装空心箱模
空心箱模的吊运可采用焊接好的敞口钢筋笼或其他箱式工具,钢筋笼内侧四边和底面用多层板封闭。按照排箱图,在每个肋梁空格内依次摆放,放置平整,前后左右对齐、对正。在箱体四周小密肋梁钢筋应保持钢筋保护层距离;或在箱体四个侧面箍筋上各放置1~2个10mm厚的小垫块,以保证箱体与小密肋梁之间的保护层厚度。对局部管线密集、管径大的部位,不能放置厚的箱模时,可換用小型薄壁空心楼板或换用聚苯板代替(聚苯板要外缠塑料胶带等保护);管线集中部位也可换小尺寸箱模避让;当预留预埋设施无法避开箱模时,可对箱模采取小型薄壁板或断开等措施,但事后应胶带和聚苯板等封堵严密。对于有些肋梁空格不满足箱模尺寸的,可将箱模锯开,空腔内填塞聚苯板等轻质材料,并用胶带封堵严密后使用。箱模安放后,应注意成品保护,避免人员频繁踩踏、破坏。破损的箱模,应在绑扎上铁前及时更换。
(9)绑扎楼板上铁
空心箱模安放完成后,即可开始绑扎楼板上铁。并与肋梁钢筋绑扎牢固。为保证抗浮点的有效,楼板上铁要压在肋梁上铁下,否则应单独设置上铁抗浮点与下铁抗浮点对应连接。
楼板上铁绑扎完毕后,在每个空心箱模顶和楼板上铁之间加设垫块,压住箱模,并保证箱模上部混凝土厚度。如下图:绑扎上铁钢筋加上铁垫块
(10)搭设施工便道、架设砼输送管
箱模本身有一定的强度,但频繁踩踏也容易造成损坏,尤其加完顶部垫块后,受力集中,易损坏。应用脚手板搭设架空施工便道,方便施工操作人员操作、通行,并保护箱模和楼板钢筋成品。
混凝土输送泵管不应直接架在楼板钢筋上,可搭设短管架子或垫木方等将泵管架高,布料杆等安放位置应提前安排好,布料杆应用脚手板和架子架高,不得直接压在箱模上。
施工机具等不得放置在空心箱模上,施工操作人员不得踩踏空心箱模。
(12)砼浇筑
现浇混凝土空心楼盖结构浇筑用混凝土,其塌落度应比普通实心楼盖稍大,可取18~20cm,不宜小于16cm;粗骨料粒径宜选择不超过5~25mm,且不大于箱模与模板间距的1/2,也不应大于肋梁宽的1/2。
箱模本身属水泥制品,在混凝土浇筑前应先洒水润湿(冬季不应洒水)。
混凝土浇筑宜采用泵送。浇筑沿楼板跨度方向从一侧开始,顺序依次进行,布料尽量均匀,避免砼在同一位置堆积过高损坏箱模。
振捣棒沿肋梁位置顺浇筑方向依次振捣,比实心楼板应适当加大振捣时间和振捣点数量,振捣同时观察空心箱模四周,直至不再有气泡冒出,表示箱模底部混凝土已密实;振捣棒应避免直接触碰空心箱模。
浇筑过程中如遇空心箱模损坏,必须及时处理。可用聚苯板、尼龙编织袋等轻质物品塞入损坏处封堵严密,注意不要使后塞物品露出箱模表面,造成混凝土夹渣。
4 施工中应注意的几个问题
1、施工中起拱方式:模板是双向板应双向起拱,单向板应单向起拱,应根据设计提供的起拱高度施工,有预应力的模板中心起拱高度在2‰。
2、空心箱体运达到施工现场后卸车时不得直接往地面上抛,堆放要整齐,不得用较重物件对空心箱体进行砸和压,放在地面和钢筋作业面上要稳定。安装空心箱体时必须轻拿轻放,在空心箱体安装过程中施工人员不得直接在空心箱体上面行走,在空心箱体上面行走之前应当铺设木板,不得直接在空心箱体上面堆放重物和其它作业。吊运安装时必须使用专用吊蓝吊运,严禁用缆绳直接绑扎空心管进行吊运,空心箱体被吊到安装楼层后应及时排放,不宜再叠层堆放。
3、振捣方法:在浇灌混凝土不宜直接在空心箱体上面堆积混凝土,放完的混凝土应立即摊开振捣、必须坚持少浇勤振,防止楼板下面出现露钢筋现象。振捣沿箱体四周的肋梁进行振捣,看见箱体中间的排气空洞中有混凝土反出,则代表下部混凝土已浇筑密实。振捣混凝土时易选用d=30的震捣棒,不得使用平板振捣器。
4、混凝土的浇筑方法:在浇筑混凝土时,应从一个角开始浇筑,依次逐步后退进行浇筑。下料时不应直接浇在空心箱体上或箱体中间的排气孔中,而是浇筑在框架梁或肋梁上。
5 结语
在几年的工程施工过程中,一直接触的都是混凝土楼板的施工,跨度都在6m~8m左右,跨距较小。在施工楼板过程中,存在十字交叉次梁或平行的次梁,给工人支设模板施工带来很多不便。与传统楼板施工技术相比,空心楼盖施工技术的最大区别与优势是: 1、施工中楼板的支模速度明显加快,整体铺放整块的模板,不用像传统楼板施工还要支设次梁的模板;
2、楼板中没有下反次梁,模板基本上不用破坏,整块拼装,使模板的周转次数明显增加,大大降低了施工成本;
3、在钢筋绑扎过程中省去了次梁,比传统提高了绑扎钢筋的成型速度,加快了施工进度。
4、在拆模过程中,比传统拆模快速方便,拆模过程不用再像以前有梁楼板不容易拆卸,拆卸后模板有碎块,模板的破损率高。采用空心箱体模板只要按顺序依次拆下,不费力气,模板完整,可以整体用到下一层去,增加了模板的周转次数、减少损耗、降低模板成本。
现浇混凝土空心楼板技术克服了传统预制混凝土空心楼板整体性差、跨度小、楼板出现裂缝、漏水,隔音不好等诸多不利因素。新技术的核浇心工艺是在现浇的楼板内放置永久的内模,节省楼板内不参与抗压抗拉等受力的混凝土,节省资源。由于整体筑,无缝隙,整体性受力非常好。另外,现浇整体空心板,比原来传统的预制空心板,在跨度方面有重大突破。在8m~15m跨度内完全不用预应力技术,降低工程成本,加快施工进度。目前该项目在新技术提供方鼎基建材(广西)科技开发有限公司的密切配合下,实施非常顺利,效果良好。同时,经常有设计单位、开发单位及施工单位前来现场观摩指导,在施工的规范程度、施工拆模后的质量、以及大空间效果等方面,得到了各界朋友的高度评价。笔者谨希望在今后的实践中,就现浇混凝土空心楼板新技术工艺的经验,与同行一起深入探讨。
参考文献:
[1]《现浇混凝土空心楼盖技术规程》,中国建筑科学研究院,中国计划出版社,2005年4月, 2.29.32.33.
[2] 建筑施工手册(第四版).[M]北京:中国建筑工业出版社,2003.
Building Construction Handbook (The fourth edition).[M]Beijing:China Architecture & Building Press, 2003.
[3] 建筑变形测量规范,JGJ8-2007,北京:中国建筑工业出版社,2007.
Code for deformation measurement of building and structure JGJ8-2007, Beijing:China Architecture & Building Press, 2007.
[4] 建筑工程冬期施工规程,JBJ/T104-2011, 北京:中国建筑工业出版社,2011.
Specification for winter construction of building engineering, JBJ/T104-2011, Beijing:China Architecture & Building Press, 2011.
[5] 混凝土结构工程施工质量验收规程,DBJ01-82-2005,北京:中國市场出版社,2005.
Specification for Acceptance of Constructional Quality of Concrete Structures, DBJ01-82-2005, Beijing:China Market Press, 2005.
[6] 建筑机械使用安全技术规程,JGJ33-2012,北京:中国建筑工业出版社,2012.
Technical specification for safety operation of constructional machinery, JGJ33-2012, Beijing:China Architecture & Building Press, 2012.
[7] 建筑节能工程施工质量验收规范,GB50411-2007,北京:中国建筑工业出版社,2007.
Code for acceptance of energy efficient building construction,GB50411-2007, Beijing:China Architecture & Building Press, 2007.